Concrete Calculator — Cubic Yards, Bags & Cost for Slabs, Footings, Columns | Anchor AI Tools

Calculators · Home & Construction

Concrete Calculator

Work out cubic yards for a slab, footing or column, see how many bags that means at each size, and get a straight answer on whether to mix by hand or order a truck. The guide below covers overage, slab thickness, and the pour-day mistakes that are expensive to undo.

Calculate your pour

Pick the shape you're pouring and enter its dimensions. Use the dropdowns to switch between feet and inches for each measurement.

Concrete needed (with overage)

0 cubic yards

Base volume

0 yd³

Cubic feet

0 ft³

Estimated cost

0

80 lb bags

0

60 lb bags

0

40 lb bags

How concrete volume is calculated

Concrete is sold by volume, in cubic yards. Every estimate comes down to working out the volume of the space you're filling and converting it into that unit — and the conversion is where nearly every mistake happens.

cubic yards = ( length × width × thickness ) ÷ 27 All three measured in feet. There are 27 cubic feet in a cubic yard (3 × 3 × 3).

The ÷ 27 catches people out because a yard is only 3 feet — so it feels like the divisor should be 3. But volume scales in three directions at once, so a cubic yard is 3 × 3 × 3 = 27 cubic feet. Skip that step and you'll order 27 times too much concrete.

The second trap is thickness in inches. Slabs are specified in inches while length and width are in feet, so the thickness has to be converted before you multiply. A 4-inch slab is 4 ÷ 12 = 0.333 feet. The calculator above handles this with the per-field unit dropdowns, but if you're doing it by hand, convert first.

Worked example — a 10 × 10 patio slab

A patio 10 ft × 10 ft poured at 4 inches thick.

Convert the thickness: 4 ÷ 12 = 0.333 ft. Volume: 10 × 10 × 0.333 = 33.3 cubic feet.

Convert to yards: 33.3 ÷ 27 = 1.23 cubic yards. Add 10% overage and order 1.36 cubic yards — in practice you'd ask the supplier for 1.5.

Footings and columns

The same principle applies, with the shape changed:

  • Strip footing — total run length × width × depth, all in feet, ÷ 27. A 40 ft run at 16 in wide and 8 in deep is 40 × 1.333 × 0.667 = 35.6 cubic feet, or 1.32 cubic yards.
  • Round column or Sonotube — π × radius² × height, ÷ 27. Radius is half the diameter, so a 10-inch tube has a 5-inch (0.417 ft) radius.
  • Multiple identical pours — calculate one, then multiply by the count. Deck footings are usually a dozen or more identical tubes.

Round columns produce deceptively small numbers. A 10-inch tube 4 feet tall holds only about 0.08 cubic yards — but fifty of them is 4 cubic yards, firmly into ready-mix territory.

Bags or ready-mix?

This is the decision the volume figure is really for, and it's worth getting right because the failure mode is unpleasant: running out of concrete halfway through a pour.

A bag of concrete mix yields far less than people expect once water is added:

Bag sizeYield per bagBags per cubic yard
80 lb≈ 0.60 cu ft45
60 lb≈ 0.45 cu ft60
40 lb≈ 0.30 cu ft90

Sit with that middle row for a second. One cubic yard is 45 eighty-pound bags — that's 3,600 lb of material, near enough 1.8 tons, that has to be lifted, mixed, and placed before the first batch starts setting. For a single person with a wheelbarrow and a mixer, that is not a realistic afternoon.

A workable rule of thumb:

  • Under ~0.5 cubic yards — bags are fine. Around 23 bags of 80 lb, manageable for one or two people.
  • 0.5 to 1 cubic yard — judgement call. Depends on how many hands you have and whether you own a mixer.
  • Over ~1 cubic yard — order ready-mix. Most suppliers have a minimum load and a short-load fee, but it's usually still cheaper than a day of hand-mixing, and vastly more consistent.

There's a quality argument too, not just a labour one. Hand-mixed batches vary — slightly different water in each one — and those variations become visible colour differences and inconsistent strength across the finished slab. Ready-mix arrives as one uniform batch.

Why you always order extra

Order about 10% more than you calculated. This isn't padding; it's the difference between a finished pour and a permanent defect. Three things eat concrete that no formula accounts for:

  • The subgrade isn't level. Nobody's gravel base is perfectly flat. Every low spot takes more concrete than the nominal thickness.
  • Forms bow outward. Wet concrete is heavy — around 4,000 lb per cubic yard — and formwork flexes under it. A slight bulge across a long form adds real volume.
  • Material is lost. Spillage from the chute, residue in the wheelbarrow, waste at the edges.

The reason this matters more than for other materials: if you run out mid-pour, the concrete already placed begins to set before the next batch arrives. The joint between them is a cold joint — a plane of weakness that doesn't bond properly and often cracks along that exact line later. You cannot fix it afterwards. Extra concrete is cheap; a cold joint through a new driveway is not.

If you do end up with surplus, have a use ready before the truck arrives — a spare paver, a post base, a small pad by the shed. Decide in advance, because you'll have about an hour.

How thick should the slab be?

Thickness drives both your volume and whether the slab survives. Standard guidance:

ApplicationTypical thicknessNotes
Patio, walkway, shed base4 inFoot traffic and light loads
Driveway, car parking5–6 inOver a compacted base
Heavy vehicles, RV pad6 in+Reinforcement usually required
Garage floor4–6 inDepends on vehicle weight

Going from 4 to 6 inches raises your concrete volume by 50%, so it's a meaningful cost decision — but under-thickness is the more expensive mistake, because a cracked slab is replaced, not repaired. Local building codes take precedence over any rule of thumb, and anything structural should be specified by an engineer rather than a calculator.

One thing worth knowing: the base under the slab matters as much as the thickness. Four inches over a well-compacted gravel base outperforms six inches poured onto soft, uncompacted ground. Concrete fails when it's unevenly supported, not usually because it's thin.

Common mistakes when estimating concrete

Forgetting to divide by 27. The single most common error. Cubic feet and cubic yards differ by a factor of 27, not 3.

Leaving thickness in inches. Convert inches to feet by dividing by 12 before multiplying, or your volume will be twelve times too large.

Using the diameter instead of the radius for columns. The formula needs radius — half the diameter. Using diameter gives four times too much concrete.

Ordering the exact calculated amount. Always add overage. Running short mid-pour creates a cold joint that permanently weakens the slab.

Underestimating bag counts. An 80 lb bag makes only about 0.6 cubic feet. Multi-yard pours by bag are far more work than they appear on paper.

Frequently asked questions

How do I calculate how much concrete I need?
Multiply length by width by thickness with all three in feet, then divide by 27 to get cubic yards. A 10 ft × 10 ft slab at 4 inches thick is 10 × 10 × 0.333 = 33.3 cubic feet, which is 1.23 cubic yards. Concrete is ordered in cubic yards, so that final conversion is the important one.
How many bags of concrete are in a cubic yard?
About 45 bags of 80 lb mix, 60 bags of 60 lb, or 90 bags of 40 lb. An 80 lb bag yields roughly 0.6 cubic feet mixed, and a cubic yard is 27 cubic feet. Yields vary slightly by brand, so check the figure printed on the bag.
Should I use bags or order ready-mix concrete?
Bags generally make sense below about half a cubic yard; ready-mix wins above roughly one cubic yard. One cubic yard is around 45 eighty-pound bags — about 1.8 tons handled by hand within a single working window — and ready-mix also gives you one consistent batch rather than dozens of slightly different ones.
How much extra concrete should I order?
Around 10% more than your calculated volume. Subgrade is never perfectly level, forms bow under the weight of wet concrete, and some material is always lost to spillage. Running short mid-pour creates a cold joint, which is a permanent weak plane, so the overage is cheap insurance.
How thick should a concrete slab be?
Four inches suits patios, walkways and shed bases. Driveways with regular car traffic are typically 5 to 6 inches, and heavy vehicles need 6 inches or more over a compacted base. Local building codes take precedence, and structural slabs should be specified by an engineer.
How much does a cubic yard of concrete weigh?
Roughly 4,000 pounds, or about two tons. This is why formwork must be braced properly and why hand-mixing large volumes is so demanding — the weight is the reason forms bow outward and add to the volume you actually need.

This concrete calculator is provided for general estimation only and is not a substitute for professional engineering advice. Bag yields vary by manufacturer — check the printed yield on your product. Confirm slab thickness, reinforcement and footing dimensions against local building codes, and consult a qualified engineer for any structural work.